Question: What is an accuratedifference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM)? Question 7 options: CPM involves more work than
What is an accuratedifference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM)?
Question 7 options:
| CPM involves more work than PERT because it requires several duration estimates | |
| CPM addresses the risk associated with duration estimates whereas PERT does not. | |
| Unlike CPM, PERT estimates only when there is no risk of uncertainty. | |
| PERT uses different duration estimates whereas CPM uses one specific duration estimate |