Question: Bruces website development project is nearing an end, and upper management must decide what to do with the resources associated with the project. Bruces team

Bruces website development project is nearing an end, and upper management must decide what to do with the resources associated with the project. Bruces team met all schedule and expenditure goals, but the product they produced (a video-swapping online destination) has underperformed in terms of ad revenue and visitors. Which form of termination would you recommend upper management consider for Bruces project?