Question: 3. Consider a project with the following: Budget at Completion (BAC): $65,000 Planned Value (PV): $ 20,000 Actual Cost (AC): $ 22,000 Earned Value (EV):

3. Consider a project with the following: Budget

3. Consider a project with the following: Budget at Completion (BAC): $65,000 Planned Value (PV): $ 20,000 Actual Cost (AC): $ 22,000 Earned Value (EV): $ 16,000 Establish the following for the project: Schedule Variance (SV) Cost Variance (CV) Schedule performance index (SPI) Cost performance index (CPI) Estimate to Complete (ETC) Estimate at Completion (EAC)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!