Question: 1 2.5 points Using the below table calculate critical path for the project. Which tasks are on the critical path? Task Predecessor Duration (Weeks) A

1 2.5 points Using the below table calculate

1 2.5 points Using the below table calculate critical path for the project. Which tasks are on the critical path? Task Predecessor Duration (Weeks) A 3 B 5 A,B 2 D 3 E 3 F 3 B OOOOO D E F 2 2.5 points Using the following table, calculate the project duration Task Predecessor Duration (days) 7 B 3 C 5 D 4 E B 2 F B,C 5 G EF 5 H F 3 Type your