Question: c ) Compare the Planned Value ( PV ) , Earned Value ( EV ) , and Actual Cost ( AC ) to calculate the
c Compare the Planned Value PV Earned Value EV and Actual Cost AC to calculate the following performance indicators: Schedule Variance SV Cost Variance CV Schedule Performance Index SPI Cost Performance Index CPI d Use the calculated CPI to estimate the Estimate at Completion EAC for the project. e Based on these metrics, provide an analysis and interpretation indicating whether the project is: Ahead of or behind schedule Over or under budget
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
