Question: c ) Quality metrics 7 - A project manager meets with a customer for initial discussions ajoct manager for a rough project. At the end
c Quality metrics
A project manager meets with a customer for initial discussions ajoct manager for a rough
project. At the end of the meeting, the customer asks the projech with three similar projects,
estimate of the project duration. Based on her exper months.
the project manager provides an estind
What estimation technique does the project manager use?
a Expert judgment
b Threepoint estimating
c Analogous estimating
d Bottomup estimating