Question: A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project
A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of months.
What estimation technique does the project manager use?
A
Bottomup estimating
B
Expert judgement
C
Analogous estimating
D
Threepoint estimating