Question: A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project

A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months.What estimation technique does the project manager use?

A. Expert judgment B. Three-point estimating C. * Analogous estimating D. Bottom-up estimating