Question: (c) We know that cycle time is 57 seconds, the productive time in a shift is 450 minutes, and TMM operates two shifts a
(c) We know that cycle time is 57 seconds, the productive time in a shift is 450 minutes, and TMM operates two shifts a day. Assume that TMM operates 5 days in a week, and there are 50 weeks in a year. What is the daily capacity of the assembly line (in number of cars)? (1) What is the weekly capacity of the assembly line (in number of cars)? (1) What is the annual capacity of the assembly line (in number of cars)? (d) Assume that the target run ratio (= utilization) is 100%. How many fewer cars are produced per shift if the run ratio is 95%? How many fewer cars are produced per shift if the run ratio is 85%? (1) (1) (1)