Question: C7Q2 is based on the same information as presented for C7Q1 Given the project information below, answer the following questions: Activity Predecessor Optimistic Time (a)

C7Q2 is based on the same information as

C7Q2 is based on the same information as presented for C7Q1 Given the project information below, answer the following questions: Activity Predecessor Optimistic Time (a) MostLikely Time (m) Pessimistic Time (b) ExpectedTime (Te) Variance A None 3 12 27 B None 8 20 26 C A 4 7 16 D A, B 27 30 45 E CD 10 13 Question C7Q2: What is the probability of completing the project in 58 periods? Fill a decimal value in the blank below (Note: rounded to 4 decimals; for e xample, 34.56% should be entered as 0.3456)