Question: Calculate earned value and efficiency for each activity and overall. Activity Budget Actual % complete Pay rate Grading 6 weeks 5 weeks 100 $40,000/week Prepare
Calculate earned value and efficiency for each activity and overall.
| Activity | Budget | Actual | % complete | Pay rate |
| Grading | 6 weeks | 5 weeks | 100 | $40,000/week |
| Prepare base | 3 weeks | 4 weeks | 100 | $20,000/week |
| Culverts | 8 weeks | 10 weeks | 100 | $30,000/week |
| Bridge | 15 weeks | 10 weeks | 67 | $80,000/week |
| Surface | 3 weeks | 1 week | 33 | $100,000/week |
| Painting | 1 week | 0 |
| $55,000/week |