Question: Calculate Estimated Duration For Each Task Develop a Time Schedule table [ [ Tasks , Predecessors,Pessimistic, table [ [ Most ] , [
Calculate Estimated Duration For Each Task
Develop a Time Schedule
tableTasksPredecessors,Pessimistic,tableMostLikelyOptimistic,tableEstimatedDurationNegotiate contract,,Install servers,Upgrade internet bandwidth,Configure software,Prepare customer data,Convert data,Train employees,GoLive,
tableStart Date,Finish Date
Construct a Network Diagram
Identify the Critical Path
Description
Using the Excel WBS provided in Canvas:
Calculate the estimated duration of each activity using the Beta distribution method Pessimistic Most Likely Optimistic
Develop a network diagram for the project.
Label the Critical Path on the network diagram.
Develop a time schedule for the project. Assume that weekends and Memorial Day are not work days.
Upload the network diagram and Excel WBS to Canvas.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock