Question: Calculate Estimated Duration For Each Task Develop a Time Schedule table [ [ Tasks , Predecessors,Pessimistic, table [ [ Most ] , [

Calculate Estimated Duration For Each Task
Develop a Time Schedule
\table[[Tasks,Predecessors,Pessimistic,\table[[Most],[Likely]],Optimistic,\table[[Estimated],[Duration]]],[1,Negotiate contract,,5,3,4,],[2,Install servers,1,20,14,12,],[3,Upgrade internet bandwidth,1,15,10,9,],[4,Configure software,1,23,19,15,],[5,Prepare customer data,1,45,20,17,],[6,Convert data,5,10,8,7,],[7,Train employees,4,6,15,13,12,],[8,Go-Live,2,3,7,12,9,7,]]
\table[[Start Date,Finish Date],[41?24,],[,],[,],[,],[,],[,],[,],[,]]
Construct a Network Diagram
Identify the Critical Path
Description
Using the Excel WBS provided in Canvas:
-Calculate the estimated duration of each activity using the Beta distribution method (Pessimistic + Most Likely*4+ Optimistic)/6.
-Develop a network diagram for the project.
-Label the Critical Path on the network diagram.
-Develop a time schedule for the project. Assume that weekends and Memorial Day are not work days.
-Upload the network diagram and Excel WBS to Canvas.
 Calculate Estimated Duration For Each Task Develop a Time Schedule \table[[Tasks,Predecessors,Pessimistic,\table[[Most],[Likely]],Optimistic,\table[[Estimated],[Duration]]],[1,Negotiate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!