Question: Calculate the Early Finish for each activity ( Forward Algorithm ) o Early Finish = Early Start + Duration for each activity o The ES

Calculate the Early Finish for each activity (Forward Algorithm)
o Early Finish = Early Start + Duration for each activity
o The ES for any activity is the greatest (latest) EF of any preceding activity, based upon the
network logic
2. Calculate the Late Finish for each activity (Backwards Algorithm)
a. Late Start = Late Finish Duration for each activity
b. The LF for any activity is the least (earliest) LS of any subsequent activity, based upon
the network logic
3. Calculate the Total Float
a. Total Float is the amount of time that an activity can be delayed without delaying
the total project
b. It is the difference between the EF and the LF for each activity
4. Identify the Critical Path
a. Those activities where TF =0 are, by definition, on the Critical Path
 Calculate the Early Finish for each activity (Forward Algorithm) o Early

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!