Question: Create the AoN and Identify the Critical Path 1 . Calculate the Early Finish for each activity ( Forward Algorithm ) o Early Finish =
Create the AoN and Identify the Critical Path
Calculate the Early Finish for each activity Forward Algorithm
o Early Finish Early Start Duration for each activity
o The ES for any activity is the greatest latest EF of any preceding activity, based upon the
network logic
Calculate the Late Finish for each activity Backwards Algorithm
a Late Start Late Finish Duration for each activity
b The LF for any activity is the least earliest LS of any subsequent activity, based upon
the network logic
Calculate the Total Float
a Total Float is the amount of time that an activity can be delayed without delaying
the total project
b It is the difference between the EF and the LF for each activity
Identify the Critical Path
a Those activities where TF are, by definition, on the Critical Path
tableABCDGHKActivity,tableDurationDaysCost $dayPreceded ByFollowed BytableEarlyStartLate Start,tableTotalFloatFree Float,tableEarlyFinishtableLateFinishA days,$ day,B days,$ day,AEC days,$ day,A days,$dayAGE days,$dayB days,$dayCI, LG days,$day days,$day days,$ day,J days,$dayG days,$dayG days,$ day,M days,$ day,J days,$dayI, days,$dayJ days,$ day, days,$day days,$day days,$dayV days,$dayVU days,$dayQVV days,$ day,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock