Question: Calculate the earned value analysis through MS project for the above information Duration (weeks) 10 8 Original Project Plan Task Immediate Predecessor H 1 H

Calculate the earned value analysis through MS

Calculate the earned value analysis through MS project for the above information

Duration (weeks) 10 8 Original Project Plan Task Immediate Predecessor H 1 H J H L J J 6 J ! EZOOM>3X>N Total Cost (SK) $ 100 $ 64 $ 96 $ 16 $ 36 $ 84 $ 80 $ 50 $ 60 $ 80 $ $ $ $ 14 $ 80 $ 24 $ 36 104 $ 66 4 2 4 4 4 5 5 5 5 3 3 1 5 2 3 8 L M M N Q o, KR U V P, W, X T, Y w $ 6 End of Week 22 Status Report Task Actual % Complete H 100% 1 100% J 100% 100% L 100% M 100% N 90% 92% 60% 50% R 50% 50% T 50% U 50% 0% W 0% 0% 0% 0% ZOOMED>3X>N Cumulative Actual Cost ($K) $ 100 $ 64 $ 96 $ 16 $ 36 $ 84 $ 80 $ 50 $ 54 $ 60 $ $ $ $ $ $ $ $ $

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!