Question: Calculate the processing load, available capacity, and develop the load profile for the stereo speaker subassembly. Two employees work the assembly process for 40 hours
Calculate the processing load, available capacity, and develop the load profile for the stereo speaker subassembly. Two employees work the assembly process for 40 hours each.
- Complete the load chart
- Prepare a load profile chart from this data.
- As the planner, what concerns do you have and what changes would you make if any?
|
| Part Name: Stereo speaker | |||||||
| Processing Time = 20 minutes | Week | Week | Week | Week | Week | Week | Week | Week |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| Planned Order Releases | 220 | 190 | 240 | 220 | 210 | 270 | 190 | 200 |
| Processing Load (hours) |
|
|
|
|
|
|
|
|
| Available Capacity (hours) |
|
|
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts