Question: Calculate the schedule using CPM method (PDM technique) and determine critical tasks Activity Successor Duration (days) A B. D E F G CD E, F

Calculate the schedule using CPM method (PDM technique) and determine critical tasksCalculate the schedule using CPM method (PDM

Activity Successor Duration (days) A B. D E F G CD E, F E, F, G H . H (with 3 days lag, i.e. H can start 3 days after finishing G) 3 5 8 6 7 7 5 H 4