Question: Calculate the values below: a. Planned value b. Actual cost c. Cost variance d. Schedule variance e. Cost performance index f. Schedule performance index g.

Calculate the values below:Calculate the values below: a. Planned value b.

a. Planned value

b. Actual cost

c. Cost variance

d. Schedule variance

e. Cost performance index

f. Schedule performance index

g. Budget at completion

h. Estimate to complete

i. Estimate at completion

Status as of Week 9 Task Budget Cost Budget Duration $5,000 1 week A 100 percent com- plete, $4,000 B $8,500 1 week 100 percent com- plete, $8,500 $15,000 2 weeks 100 percent com- plete, $14,000 D $10,000 2 weeks 50 percent com- plete, $9,000 50 percent com- plete, $12,000 E $12,000 3 weeks F $15,000 2 weeks Not started

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!