Question: Calculate the values below: a. Planned value b. Actual cost c. Cost variance d. Schedule variance e. Cost performance index f. Schedule performance index g.
Calculate the values below:
a. Planned value
b. Actual cost
c. Cost variance
d. Schedule variance
e. Cost performance index
f. Schedule performance index
g. Budget at completion
h. Estimate to complete
i. Estimate at completion
Status as of Week 9 Task Budget Cost Budget Duration $5,000 1 week A 100 percent com- plete, $4,000 B $8,500 1 week 100 percent com- plete, $8,500 $15,000 2 weeks 100 percent com- plete, $14,000 D $10,000 2 weeks 50 percent com- plete, $9,000 50 percent com- plete, $12,000 E $12,000 3 weeks F $15,000 2 weeks Not startedStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
