Question: Calculate the work done and the Earned Value at the end of two weeks in the following situation: Time estimated to complete project: 1 0

Calculate the work done and the Earned Value at the end of two weeks in the following situation:
Time estimated to complete project: 100 hours
Duration of project: 4 weeks
Planned value: 25 hours per week
Actual time required over the first two weeks: 60
Actual time required to finish the project: 80
Work done = Blank 1%
Earned value = Blank 2 hours