Question: Camela is checking her project plan for any potential problems. Which filter should she use to identify tasks that are falling behind and which have
Camela is checking her project plan for any potential problems. Which filter should she use to identify tasks that are falling behind and which have more work than planned?Select an answer:Slipping Tasks filterShould Start By filterWork Over Budget filterSlipLate Progress filter