Question: Q1: Jake is working on his project plan, and adding resources to it. He needs to add rented equipment and some temporary staffing. Which type
Q1: Jake is working on his project plan, and adding resources to it. He needs to add rented equipment and some temporary staffing. Which type of resource is he adding, and what is true about the cost? Select an answer:
He is adding the cost resource. He should apply the cost when he assigns the cost resource.
He is adding the project resource. The costs will not affect the project.
He is adding the work resource. The costs will affect the labor cost for the project.
He is adding the material resource. He should add the quantity and cost per unit.
Q2:
Camela is checking her project plan for any potential problems. Which filter should she use to identify tasks that are falling behind and which have more work than planned?
Select an answer:
-
Slipping Tasks filter
-
Should Start By filter
-
Work Over Budget filter
-
Slip/Late Progress filter