Question: can someone help on part d its not .7781 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your

c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. Answer is complete and correct. d. What is the probability of completing this project within 16 days? Note: Use Excel's NORMSDIST0 function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round " z " value to 2 decimal places and final answer to 4 decimal places. Answer is complete but not entirely correct. The following represents a project that should be scheduled using CPM: b. What is the critical path? A-D.G-H A-C.F.H B-E.G-H A.D.F.H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places