Question: Can this question please be answered using values in this question, read all parts of the question as the previous solution just gave the steps





Can this question please be answered using values in this question, read all parts of the question as the previous solution just gave the steps and used different values. The solution should be provided using the values in this question.
The following data have been collected for a British health care IT project for two-week reporting periods 2 through 12. Compute the SV, CV, SPI, CPI, and PCIB for each period. 14 7 18 42 12 2 2 o 0 6 8 od 14 14 4 18 0 1 4 18 8 22 10 5 14 0 0 o 4 3 10 0 0 4 6 10 0 Oo |o. 4 4 10 4 4 14 4 22 Legend ESID EF 4 48 86 16 2 2. 2 2 SL SL 6 4 10 10 8 18 LS DUR LF Baseline (PV) ($00) PV Task DUR ES LF SL ($00) 2 4 6 8 10 12 14 16 18 20 22 1 4 0 4 0 00 4 4 2 00 4 14 2 40 10 10 10 10 3 6 4 10 0 30 10 15 5 4 4 4 10 2 20 10 10 NO 5 4 10 14 40 20 20 6 00 8 18 2 60 2020 10 10 7 4 14 18 0 20 10 10 8 8 4 18 22 0 30 20 10 Period PV total 4 4 30 35 | 35 | 50 | 30 20 10 20 8 10 Cumulative PV total 4 00 8 38 73 108 158 188 208218238 248 (Do not round intermediate calculations. Enter all values to 2 decimal precision. For SPI, CPI, and PCI-B, enter in decimals rather than percentage format. (i.e., enter 0.93 if the answer is 93%)) End of Period 2 Task EV AC PV SV Actual % Complete 40 1 5.00 Cumulative Totals End of Period 4 Task Actual % Complete EV PV SV AC 10.00 1 100 Cumulative Totals End of Period 6 Task EV AC PV CV SV Actual % Complete 100 1 10.00 2 20 15.00 3 35 11.00 4 0 0.00 Cumulative Totals End of Period 8 Task Actual % Complete EV AC PV SV 1 100 10.00 2 40 18.00 3 50 20.00 4 0 0.00 Cumulative Totals End of Period 10 Task Actual % Complete EV AC PV CV SV 1 100 10.00 2 70 30.00 3 100 40.00 4 50 20.00 5 0 0.00 0.00 0.00 0.00 0.00 6 30 25.00 Cumulative Totals End of Period 12 Task EV AC PV CV SV Actual % Complete 100 1 10.00 2 100 50.00 3 100 40.00 40.00 4 100 5 50 25.00 6 40 24.00 45.00 40.00 (21.00) (16.00) Cumulative Totals Performance Indexes Summary Period EV AC PV SPI CPI PCI-B 2 4 6 8 10 12 EACE VACE =Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
