Question: can you please answer all questions MGT 413 Chapter 3 Homework. A project consists of the following activities. Immediate Predecessor(s) Activit Duratio n A 3
can you please answer all questions
MGT 413 Chapter 3 Homework. A project consists of the following activities. Immediate Predecessor(s) Activit Duratio n A 3 B 11 7 A D 13 B, C E 10 B F 6 6 D G 5 E H 8 EF (a) (b) Draw the PERT/CPM network diagram for the project. Determine and state the earliest start time, earliest finish time, latest finish time, and latest start time for each activity in the project. ). Determine the slack for each activity. (d) List the critical path activities for this project. (e) What is the project completion duration