Question: NOTE: Please CLEARLY answer all parts A through E. Please record your answer next to the question . Also, draw the diagram out clearly so

NOTE: Please CLEARLY answer all parts A through E. Please record your answer next to the question. Also, draw the diagram out clearly so that it can be understood! Thank you kindly!
MGT 413 Chapter 3 Assignment A project consists of the following activities. Immediate Predecessor(s) Activity Duration A 7 B 2 4 A A B, C D E E E F G 4 3 5 (a). Draw the PERT/CPM network diagram for the project. (b). Determine and state the earliest start time, the earliest finish time, the latest finish time, and the latest start time for each activity in the project. (c). Determine the slack for each activity. (d). List the critical path activities for this project. (e) What is the project completion durationStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts