Question: Can you please explain how to get the correct answer Four jobs were queued at a workstation with the listed profiles. Job 1 2 3

Can you please explain how to get the correct answerCan you please explain how to get the correct

Four jobs were queued at a workstation with the listed profiles. Job 1 2 3 4 Processing Time 8.9 5.4 2.7 12.3 Time to Due Date 18 10 20 8 No OPNS remaining 5 2 3 4 Shop Time Remaining 17.3 7.7 15.5 9.5 Using the critical-ratio-priority sequencing rule, determine the average past-due time for the current workstation. A. 6.400 OB. 5.325 C. 8.4 OD. 7.475