Question: Cans are made in a process with two resources. The first resource has a capacity of 2.3 cans per second. The capacity of the second
Cans are made in a process with two resources. The first resource has a capacity of 2.3 cans per second. The capacity of the second resource is 2.1 cans per second. The first resource has 1 worker and the second resource has 9 workers.
What is the labor content (in seconds)? round to 2 decimal places