Canvas - XC D Question 26 1 pts In context of project scheduling and estimating the duration of a project's activities answer the following question: Formulas for calculating variance and expected time calculations: TE- 6 Consider the following information about activity A Activity Expected Time Standard Deviation Optimistic Time 3 Most Likely Time 5 Pessimistic Time 12 A Y What are X and Y respectively? 5.33.225 225.5.83 583.15 15.5.83 Question 27 1 pts 5 W E R T . S DF G H J K Z X CV B N M