Question: Case Study: Attempts in Varying Degrees to Capture All Effort The Government Accountability Office ( GAO ) in the United States government analysed four enterprise
Case Study: Attempts in Varying Degrees to Capture All Effort
The Government Accountability Office GAO in the United States government analysed four
enterprise resource planning system schedules and found that none of the programs had developed
a fully integrated master schedule as an effective tool to help in the management of the programs.
In particular, the schedules differed in the extent to which they captured all activities, as well as in
their integration of government and contractor activities. For example, the Defence Enterprise
Accounting and Management System Program Management Office did not have a schedule that
integrated government and contractor activities. It maintained internal schedules that reflected
governmentonly activities, but these activities were not linked to the contractors activities. While the
Armys Global Combat Support System schedule identified contractor activities, it contained only key
government milestones for the program. Other government activities, such as testing events and
milestones beyond December were not captured in the schedule. Instead, they were displayed
in isolated, highlevel illustrated documents.
The Expeditionary Combat Support System program schedule contained detailed activities
associated with government
effort and contractor effort. However, the government activities were not fully linked to contractor
activities, so that updates to government activities did not directly affect scheduled contractor
activities. Finally, while the General Fund Enterprise Business System schedule captured
government and contractor activities, key milestones in deployment, software release, and
maintenance were not fully integrated, precluding a comprehensive view of the entire program.
In scheduling, best practices are interrelated so that deficiencies in one best practice cause
deficiencies in other best practices. For example, if the schedule does not capture all activities, then
there will be uncertainty about whether activities are sequenced in the correct order and whether the
schedule properly reflects the resources needed to accomplish the work.
You have been appointed as the consulting project manager to the GAO. Having examined
the various issues with the four enterprise resource planning system schedules, advise on
scheduling best practice that the GAO can adopt in order to ensure that they produce a
realistic schedule that will deliver acceptable results. Marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
