Question: Case Study: Attempts in Varying Degrees to Capture All Effort The Government Accountability Office ( GAO ) in the United States government analysed four enterprise

Case Study: Attempts in Varying Degrees to Capture All Effort The Government Accountability Office (GAO) in the United States government analysed four enterprise resource planning system schedules and found that none of the programs had developed a fully integrated master schedule as an effective tool to help in the management of the programs. In particular, the schedules differed in the extent to which they captured all activities, as well as in their integration of government and contractor activities. For example, the Defence Enterprise Accounting and Management System Program Management Office did not have a schedule that integrated government and contractor activities. It maintained internal schedules that reflected government-only activities, but these activities were not linked to the contractors activities. While the Armys Global Combat Support System schedule identified contractor activities, it contained only key government milestones for the program. Other government activities, such as testing events and milestones beyond December 2017, were not captured in the schedule. Instead, they were displayed in isolated, high-level illustrated documents. The Expeditionary Combat Support System program schedule contained detailed activities associated with government effort and contractor effort. However, the government activities were not fully linked to contractor activities, so that updates to government activities did not directly affect scheduled contractor activities. Finally, while the General Fund Enterprise Business System schedule captured government and contractor activities, key milestones in deployment, software release, and maintenance were not fully integrated, precluding a comprehensive view of the entire program. In scheduling, best practices are interrelated so that deficiencies in one best practice cause deficiencies in other best practices. For example, if the schedule does not capture all activities, then there will be uncertainty about whether activities are sequenced in the correct order and whether the schedule properly reflects the resources needed to accomplish the work. As a project manager, what are the benefits of using a Gantt chart and also describe two major shortcomings of this tool?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!