Question: Case study on Ariba Implementation at MED-X: Managing Earned Value (Case study can be found on the website) Your team has been assigned to help
Case study on "Ariba Implementation at MED-X: Managing Earned Value" (Case study can be found on the website)
Your team has been assigned to help Christopher Martin determine what went wrong with the project and develop a presentation and recommendation for Terry Baker.
Questions:
- Which of the two components is underperforming according to the plan? How do you know this?
- Are the components of the project within the budget? How do you know?
- What can you conclude by looking at the combined earned value data for the project?
- Why did Terry Baker think that the project was going according to plan the entire time?
- How much longer will the project take?
- What should Martin have done earlier in the project timeline to prevent delays?
- What should Martin do when managing future projects to prevent similar problems from developing?