Question: Which two things would allow you to calculate a projects cost estimate at completion (EAC)? Select 2 answers. A. Forecasted spending for the remainder of
Which two things would allow you to calculate a projects cost estimate at completion (EAC)? Select 2 answers.
A. Forecasted spending for the remainder of the project
B. Timeline of the project from start to finish
C. Priority order of the remaining project activities
D. Actual costs of the project to date
E. Labor cost estimate for the remainder of the project
F. Deadlines for each remaining project activity