Question: CCMN 2 0 4 0 Construction Project Management Lab Assignment 5 Case Study: Dare County Justice Center | Dare County, North Carolina, a re -
CCMN Construction Project
Management
Lab Assignment
Case Study: Dare County Justice Center
Dare County, North Carolina, a re mote Outer
Banks community located miles from Norfolk,
Virginia and miles from Raleigh, North Carolina,
required a stateoftheart justice facility to replace
its existing yearold courthouse and associated
warren of converted grocery store and motel
buildings pressed into service as court support
facilities. The result is a squarefoot, two
story justice facility, which includes the county tax
offices, Register of Deeds, probation, Sheriff's
office, holding cells, five courtrooms and Clerk of
Court offices with support facilities. The
construction period was from May to October
The role of the courthouse in this small community
made this a particularly significant project for the
Dare County Justic Center Manteo, North Carolina
Contractor: Heery International
Services: Design and Construction Management
County. The primary users of the justice center judges, clerk of the court, sheriff, register of
deeds, and the general public either having their day in court or performing jury dutyhad distinct
opinions on how the new facility should look and operate.
While creating an exemplary, uptodate justice center that would be a model for other
communities, Heery's project team was also charged with meeting other goals. Dare County
wanted the justice center to present an appropriate civic image, as well as incorporate features
in keeping with the community's expectations for the facility to reflect Dare County's rich
heritage and history. Heery provided programming, planning and design, and singlesource
design build services. The team used an Integrated Project Delivery IPD also known as
LEAN, approach to the project.
The new justice center is located at the end of the new Highway bridge, meaning that the
justice center is the first thing visitors to Roanoke Island part of Dare County see. Extensive
architectural detailing on three sides presents an appropriate courthouse image. Elements of
the old courthouse design such as columns and the use of brick are incorporated into the new
building to give it this local, historical reference point. Other local design features include a
terrazzo map of Dare County at the main lobby entrance, symbolic light house design for in the
inside lobby, balcony columns, and extensive landscaping to blend with Manteo's citywide
approach to landscaping.
CCMN Construction Project
Management
Lab Assignment
Name:
Date:
Instructions: Imagine Dare County selected your company as the construction manager for the
Dare County Justice Center project. The owner has not designed the facility and needs your
company to define the scope of the project. As the Senior Project Manager for the project, it is
your responsibility to develop a workable purpose, approach and feasible limits Read the
following Dare County Justice Center Case Study and answer the questions below.
What is the use of the project and what functions will it serve?
Why is the project being built?
What is the scale, "look and feel" and nature of the project?
What questions would you ask based on intuition and quantitative impressions to find the
best "workable approach"?
What are some of the project ingredients you must consider?
Is risk evaluation for the project necessary? If so explain your answer.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock