Question: Certity I CSE 1 COMS _ CIS 1 5 1 3 C 7 2 5 1 4 4 [ Based on CompTIA Project + (
Certity I CSECOMSCISCBased on CompTIA ProjectPR
Which of the following is not a costestimating technique?
RFP
Bottomup estimating
SIPOCR