Question: ch15 PSB Consider the following information about a small project: B. pictureclick here for the Excel Data File b-1. Identify the critical path. A-B-C-FA-D-E-FA-B-E-F b.2.
ch15 PSB
Consider the following information about a small project: B. pictureclick here for the Excel Data File b-1. Identify the critical path. A-B-C-FA-D-E-FA-B-E-F b.2. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" c. Which of these activities should the project manager track most closely? A-B-C-F A-B-E-F A-D-E-F