Question: Task Duration Estimates Immediate Predecessors A 2 days None B 5 days A C 1 day B D 2 days A E 3 days B
Task Duration Estimates Immediate Predecessors
A days None
B days A
C day B
D days A
E days B and D
F days E and C
Click here for the Excel Data File
b Identify the critical path.
b Identify the earliest start and finish.
b Identify the slack for each task.
c Which of these activities should the project manager track most closely?