Question: Task Duration Estimates Immediate Predecessors A 2 days None B 5 days A C 1 day B D 2 days A E 3 days B

Task Duration Estimates Immediate Predecessors
A 2 days None
B 5 days A
C 1 day B
D 2 days A
E 3 days B and D
F 12 days E and C
Click here for the Excel Data File
b-1. Identify the critical path.
b-2. Identify the earliest start and finish.
b-3. Identify the slack for each task.
c. Which of these activities should the project manager track most closely?