Question: Answer the following questions. Task A Duration Estimates Immediate Predecessors None 2 days B 5 days A C 1. day B D 2 days A

 Answer the following questions.

Task A Duration Estimates Immediate Predecessors None 2 days B 5 days 

Task A Duration Estimates Immediate Predecessors None 2 days B 5 days A C 1. day B D 2 days A E 3 days B and D F 12 days E and C o Click here for the Excel Data File b-1. Identify the critical path. b-2. Identify the earliest start and finish. b-3. Identify the slack for each task. c. Which of these activities should the project manager track most closely?