Question: (CH6) For the project activities shown in the project schedule network diagram, duration times are given as weeks in parentheses: A(7), B(3), C(6), D(3), E(5),

(CH6) For the project activities shown in the

(CH6) For the project activities shown in the project schedule network diagram, duration times are given as weeks in parentheses: A(7), B(3), C(6), D(3), E(5), F(2), G(3),H(2). Which of the following is the critical path? H B D E a. A-C-E-H b. B-D-E-H C. A-C-G-H d. B-F-E-H