Question: (Ch6) You are using a triangular estimate for your project. Howard reports that his optimistic estimate is 16 hours, his most likely estimate is 24

(Ch6) You are using a triangular estimate for
(Ch6) You are using a triangular estimate for your project. Howard reports that his optimistic estimate is 16 hours, his most likely estimate is 24 hours, and the pessimistic estimate is 65 hours. What is the estimated duration for Howard's activity? a. You won't know until Howard actually does the work. .b. 105 hours. c. 24 hours d. 35 hours