Question: A Project Manager is employing a triangular estimate for his project. He has determined that the optimistic estimate is 1 6 0 hours, the most

A Project Manager is employing a triangular estimate for his project. He has determined that the optimistic estimate is 160 hours, the most likely estimate is 240 hours, and the pessimistic estimate is 650 hours. What is the estimated duration for project?Group of answer choicesThe duration hours cannot be determined until the work has been completed1,050 hours350 hours240 hours