Question: CH7-014: Given BAC - 200, PV - 100, AC-120, EV-80. Assuming that what the project has experienced to date can be expected to continue in

CH7-014: Given BAC - 200, PV - 100, AC-120,
CH7-014: Given BAC - 200, PV - 100, AC-120, EV-80. Assuming that what the project has experienced to date can be expected to continue in the future, the variance at completion (VAC) IS: -80, -100 -100 +200. the stone save the MacBook Air