Question: Y ou are working on a project that has the following data: BAC = 200 PV = 100 AC = 120 EV =80 Assuming that

Y ou are working on a project that has the following data: BAC = 200 PV = 100 AC = 120 EV =80 Assuming that what the project has experienced to date can be expected to continue in the future, the estimate at completion (EAC) is:

A. 325 B. 375 C. 350 D. 300

Note: Please show formula worked in your explanation.