Question: Champion Cooling has just signed a contract to assemble window air conditioners for another company. The list of tasks, including time requirements and immediate predecessors,
Champion Cooling has just signed a contract to assemble window air conditioners for another company. The list of tasks, including time requirements and immediate predecessors, follows. Each task may not be shortened. The plan is to make units in an eight hour day. What should their takt time be
tableTaskTime minPredecessorBolt compressor to base,NoneInstall coils and lines,Bolt compressor to baseInstall fan motor,Install coils and linesInstall switch and thermostat,Install fan motorCharge system and test,Install switch and thermostatCosmetic detailing,Charge system and test