Question: Chapter 0 4 Question: 0 1 The table below lists the work elements in minutes to be performed on assembly line with precedence requirements. Annual

Chapter 04
Question: 01
The table below lists the work elements in minutes to be performed on assembly line with precedence requirements. Annual demand is 60000 units. The line will operate on shift with available time (2000hryr. Line efficiency is expected to be 95% and repositioning time is 6 sec . The table below defines the precedence relationships and element times for a new model toy. (a) Construct the precedence diagram for this job. (b) what is the theoretical minimum number of workstations required to minimize the balance delay under the assumption that there will be one worker per station? (c) Use the largest candidate rule to assign work elements to stations. (d) Compute the balance delay for your solution.(e) What will be the production rate ?hr after the line is balanced.
\table[[Work element,Te(min),Immediate predecessors],[1,0.5,-],[2,0.3,-],[3,0.8,1],[4,1.1,1,2],[5,0.6,2],[6,0.2,3],[7,0.7,4],[8,1.0,5],[9,1.2,5],[10,0.4,6],[11,0.9,7],[12,0.1,8,9],[13,1.3,10,11,12
 Chapter 04 Question: 01 The table below lists the work elements

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!