Question: Chapter 1 6 Use the information provided in the Table 1 and the network diagram in Figure 1 for the following problems. Activity Normal Time
Chapter
Use the information provided in the Table and the network diagram in Figure for the following problems.
Activity Normal Timeweeks Normal Cost $ Crash Time weeks Crash Cost $ Maximum weeks Reduced Crash Cost per Week $
A
B
C
D
E
F
G
Using the informatiChapter
Use the information provided in the Table and the network diagram in Figure for the following problems.
Activity Normal Timeweeks Normal Cost $ Crash Time weeks Crash Cost $ Maximum weeks Reduced Crash Cost per Week $
A
B
C
D
E
F
G
Using the information given,
Ideology for Problem is sourced from textbook page Table Reid and Sanders,
o Calculate the completion time of the project.
Path : ABEGH weeks
Path : ACEGH weeks
Path : ACFGH weeks
Path : ADFGH weeks
Completion Time longest production path weeks
o Identify the activities on the critical path.
Activities on the Critical Path ACFGH
Using the information given and the project completion time calculated in Problem reduce the completion time of the project weeks in the most economical way.
The least expensive critical path activity to crash is activity G Based on the above table, we can crash activity G for a maximum of weeks at a cost of $ per week.
Total Crash Cost to reduce time of project completion by weeks $ weeks $
Using the information given and the project completion time calculated in Problem calculate the minimum time for completing the project possible.on given,
Ideology for Problem is sourced from textbook page Table Reid and Sanders,
o Calculate the completion time of the project.
Path : ABEGH weeks
Path : ACEGH weeks
Path : ACFGH weeks
Path : ADFGH weeks
Completion Time longest production path weeks
o Identify the activities on the critical path.
Activities on the Critical Path ACFGH
Using the information given and the project completion time calculated in Problem reduce the completion time of the project weeks in the most economical way.
The least expensive critical path activity to crash is activity G Based on the above table, we can crash activity G for a maximum of weeks at a cost of $ per week.
Total Crash Cost to reduce time of project completion by weeks $ weeks $
Using the information given and the project completion time calculated in Problem calculate the minimum time for completing the project possible.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
