Question: Chapter 1 6 Use the information provided in the Table 1 and the network diagram in Figure 1 for the following problems. Activity Normal Time

Chapter 16
Use the information provided in the Table 1 and the network diagram in Figure 1 for the following problems.
Activity Normal Time(weeks) Normal Cost ($) Crash Time (weeks) Crash Cost ($) Maximum weeks Reduced Crash Cost per Week ($)
A 455039502450
B 565047502150
C 7850413504550
D 71550522003100
E 71800523003550
F 62506125011050
G 81550618503350
1. Using the informatiChapter 16
Use the information provided in the Table 1 and the network diagram in Figure 1 for the following problems.
Activity Normal Time(weeks) Normal Cost ($) Crash Time (weeks) Crash Cost ($) Maximum weeks Reduced Crash Cost per Week ($)
A 455039502450
B 565047502150
C 7850413504550
D 71550522003100
E 71800523003550
F 62506125011050
G 81550618503350
1. Using the information given,
**Ideology for Problem 1 is sourced from textbook page 586, Table 16.6(Reid and Sanders, 2023).**
o Calculate the completion time of the project.
Path 1: A-B-E-G-H =4+3+5+4+3=19 weeks
Path 2: A-C-E-G-H =4+5+5+4+3=21 weeks
Path 3: A-C-F-G-H =4+5+6+4+3=22 weeks
Path 4: A-D-F-G-H =4+2+6+4+3=19 weeks
Completion Time =(longest production path)=22 weeks
o Identify the activities on the critical path.
Activities on the Critical Path = A,C,F,G,H
2. Using the information given and the project completion time calculated in Problem 1, reduce the completion time of the project 3 weeks in the most economical way.
The least expensive critical path activity to crash is activity G. Based on the above table, we can crash activity G for a maximum of 3 weeks at a cost of $350 per week.
Total Crash Cost to reduce time of project completion by 3 weeks = $350*3 weeks = $1,050
3. Using the information given and the project completion time calculated in Problem 1, calculate the minimum time for completing the project possible.on given,
**Ideology for Problem 1 is sourced from textbook page 586, Table 16.6(Reid and Sanders, 2023).**
o Calculate the completion time of the project.
Path 1: A-B-E-G-H =4+3+5+4+3=19 weeks
Path 2: A-C-E-G-H =4+5+5+4+3=21 weeks
Path 3: A-C-F-G-H =4+5+6+4+3=22 weeks
Path 4: A-D-F-G-H =4+2+6+4+3=19 weeks
Completion Time =(longest production path)=22 weeks
o Identify the activities on the critical path.
Activities on the Critical Path = A,C,F,G,H
2. Using the information given and the project completion time calculated in Problem 1, reduce the completion time of the project 3 weeks in the most economical way.
The least expensive critical path activity to crash is activity G. Based on the above table, we can crash activity G for a maximum of 3 weeks at a cost of $350 per week.
Total Crash Cost to reduce time of project completion by 3 weeks = $350*3 weeks = $1,050
3. Using the information given and the project completion time calculated in Problem 1, calculate the minimum time for completing the project possible.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!