Question: Chapter 16 Use the information provided in the Table 1 and the network diagram in Figure 1 for the following problems. Activity Normal Time(weeks) Normal

Chapter 16

Use the information provided in the Table 1 and the network diagram in Figure 1 for the following problems.

Activity Normal Time(weeks) Normal Cost ($) Crash Time (weeks) Crash Cost ($) Maximum weeks Reduced Crash Cost per Week ($)
A 4 550 3 950 2 450
B 5 650 4 750 2 150
C 7 850 4 1350 4 550
D 7 1550 5 2200 3 100
E 7 1800 5 2300 3 550
F 6 250 6 1250 1 1050
G 8 1550 6 1850 3 350

Table 1

Figure 1. AON network diagram

  1. Using the information given,
    • Calculate the completion time of the project.
    • Identify the activities on the critical path.
  2. Using the information given and the project completion time calculated in Problem 1, reduce the completion time of the project 3 weeks in the most economical way.
  3. Using the information given and the project completion time calculated in Problem 1, calculate the minimum time for completing the project possible.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!