Question: (Chapter 19 Project Crashing in Project Management) Two activities are candidates for crashing. The activity details are in the table below. To reduce project completion

(Chapter 19 Project Crashing in Project
(Chapter 19 Project Crashing in Project Management) Two activities are candidates for crashing. The activity details are in the table below. To reduce project completion time by one day, which activity should be crashed first? How much will this add to the total project cost? Crash activity B; This adds $2,000 to total project cost. Crash activity C; This adds $1,000 to total project cost. Crash activity C: This adds $2,000 to total project cost. Crash activity B; This adds $8,000 to total project cost