Question: (Chapter 19 Project Management with Activity Time Uncertainty) A project consists of 6 activities: A, B, C, D, E, and F. The project network is

(Chapter 19 Project Management with Activity Time
(Chapter 19 Project Management with Activity Time Uncertainty) A project consists of 6 activities: A, B, C, D, E, and F. The project network is shown below. A, B, C, E, and F are known to take 4 days each. However, D takes 4 days with a probability of 75% and 8 days with a probability of 25%. What is the expected project completion time? 28 days 13 days 16 days 10 days