Question: Chapter 3 In a batch machining operation, setup time is 1.5 hours and batch size is 80 units. The cycle time consists of part handling
Chapter 3
In a batch machining operation, setup time is 1.5 hours and batch size is 80 units. The cycle time consists of part handling time of 30 sec and processing time of 1.37 min. One part is produced each cycle. Tool changes must be performed every 10 parts and this takes 2.0 min. Determine (a) average cycle time, (b) time to complete the batch, and (c) average production rate.
Solve for :
a: Cycle time = ? minutes
b: Batch Time = ? per hour
c: Average Production Time: ? Minutes/piece
Typical cycle time for a production operation: Tc = To + Th + Tth
where Tc = cycle time,
To = processing time for the operation
Th = handling time (e.g., loading and unloading the production machine)
Tth = tool handling time (e.g., time to change tools)
Batch production: batch time Tb = Tsu + QTc
Average production time per work unit Tp = Tb/Q
Tsu = setup time
Production rate Rp = 1/Tp
Job shop production: For Q = 1, Tp = Tsu + Tc (Q=80 units)
For quantity high production: Rp = Rc = 60/Tp
For flow line production : Tc = Tr + Max To and Rc = 60/Tc
Group of answer choices
a=2.07 minutes b= 4.26 hrs c= 3.2 min/piece
a=2.07 minutes b= 4.26 hrs c= 4.0 min/piece
a=2.07 minutes b= 4.75 hrs c= 3.2 min/piece
None of the above