Question: Chapter 3 In a batch machining operation, setup time is 1.5 hours and batch size is 80 units. The cycle time consists of part handling

Chapter 3

In a batch machining operation, setup time is 1.5 hours and batch size is 80 units. The cycle time consists of part handling time of 30 sec and processing time of 1.37 min. One part is produced each cycle. Tool changes must be performed every 10 parts and this takes 2.0 min. Determine (a) average cycle time, (b) time to complete the batch, and (c) average production rate.

Solve for :

a: Cycle time = ? minutes

b: Batch Time = ? per hour

c: Average Production Time: ? Minutes/piece

Typical cycle time for a production operation: Tc = To + Th + Tth

where Tc = cycle time,

To = processing time for the operation

Th = handling time (e.g., loading and unloading the production machine)

Tth = tool handling time (e.g., time to change tools)

Batch production: batch time Tb = Tsu + QTc

Average production time per work unit Tp = Tb/Q

Tsu = setup time

Production rate Rp = 1/Tp

Job shop production: For Q = 1, Tp = Tsu + Tc (Q=80 units)

For quantity high production: Rp = Rc = 60/Tp

For flow line production : Tc = Tr + Max To and Rc = 60/Tc

Group of answer choices

a=2.07 minutes b= 4.26 hrs c= 3.2 min/piece

a=2.07 minutes b= 4.26 hrs c= 4.0 min/piece

a=2.07 minutes b= 4.75 hrs c= 3.2 min/piece

None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!