Question: Chapter 5 Exercises 127 Activity Duration Type Rela Lag ES EF LS LF TF FF A B SS 3 C SS 1 7 6 A

Chapter 5 Exercises 127 Activity Duration Type Rela Lag ES EF LS LF TF FF A B SS 3 C SS 1 7 6 A 2 B 6 C 10 D D A FF B FF FF D FF SS E 3 SS 2. if the relationship type is not mentioned, it is finish to start (FS). If no lag is mentioned, it is zero. 16. Prove that using interruptible activities in the following project allows the projec to finish 5 days earlier than if the activities were contiguous
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts